P150 pool progress

Three of the six 22 metre-long Westlock beams that span the pool and viewing gallery were installed on Monday 3 April. The remaining three will be added on Monday 10 April.

The current target is to have all of the construction steel and floors in place by mid- May.

 

 

 

Other works currently ongoing include the roof decking and weatherproofing to the north half of the building, blockwork to the basement areas and sports hall and commencement of the face brickwork and flint panels.

Three of the five staircases have also been installed.